White balance 59×400R
The crane is designed for mechanization of loading and unloading operations on drilling rigs, pipe sockets, construction sites, and workshops. In the trapezoidal design, it is used as part of the auxiliary lifting equipment of the drilling rig.
Gallery
Hook lifting capacity, with 6×7 rigging, kN |
4000 |
design |
From the pipeline |
Lattice system |
Rigid support cross |
Total height, m |
62.35 |
Top height of crane frame, m |
58.35 |
Lower foot size along the leg axis, m |
10 × 10 |
Opening height of gate, m |
10.5 |
Balcony height, meters |
23 and 35 |
Magazine capacity of the tube, m |
Ø127 applies 5000 |